600 watts, a notification duty, and the plug question
Plug-in solar systems up to 600 W are permitted but must be notified to the local grid operator.
- Inverter
- max. 600 W AC
- Grid operator notice
- required
- Plug type
- T13 / T23, not Schuko
Show detailsHide details
Switzerland did not raise the limit to 800 W; 600 W of inverter output remains the ceiling. An 800 W device imported from Germany must be throttled accordingly.
Connection uses a Swiss T13 or T23 plug. German Schuko plugs do not fit Swiss sockets, and a bare adapter is not a clean solution.
Notifying the grid operator is mandatory and usually free. Some utilities additionally require the work to be carried out by an authorised person.